    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefits and valuebenefits realizationvalue deliveryprocess optimizationbusiness outcomes

    PMP · Question 69 · Task 2: Evaluate and deliver project benefits and value

    A project manager has completed a enterprise resource planning (ERP) system implementation. The system is functioning correctly and meets all technical specifications. However, eight months after go-live, user adoption remains lower than expected, business processes haven't been optimized as planned, and the anticipated benefits of improved efficiency and cost reduction have not materialized. What should the project manager do FIRST?

    Answer options:

    A.

    Provide additional user training and change management support to increase system adoption

    B.

    Enhance the ERP system with additional features and customizations to increase user value

    C.

    Conduct a comprehensive benefits realization assessment to identify specific barriers to value achievement and process optimization

    D.

    Extend the benefits measurement period since organizational change and process optimization take time to mature

    How to approach this question

    Look for systematic approaches that analyze why expected benefits aren't being realized and identify specific barriers to value achievement and process optimization.

    Full Answer

    C.Conduct a comprehensive benefits realization assessment to identify specific barriers to value achievement and process optimization✓ Correct
    Effective benefits realization requires systematic assessment of why expected value isn't being achieved, identification of specific barriers to benefits realization, and understanding of process optimization challenges.

    Common mistakes

    Students often choose training or enhancement approaches rather than recognizing the need to analyze barriers to benefits realization and process optimization.
    Question 68All questionsQuestion 70

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →