    Hard1 markMultiple Choice
    Task 2: Manage communicationscommunication managementstakeholder analysiscomplex integrationcommunication matrix

    PMP · Question 88 · Task 2: Manage communications

    A project manager is leading a complex system integration involving multiple vendors, internal departments, and regulatory agencies. Each stakeholder group has different information requirements, communication preferences, decision-making timelines, and reporting needs. Recent communication breakdowns have led to misaligned expectations and project delays. What should the project manager do FIRST?

    Answer options:

    A.

    Implement a centralized project communication portal where all stakeholders can access comprehensive project information

    B.

    Develop a detailed stakeholder communication matrix that specifies content, channels, frequency, timing, and feedback mechanisms for each group

    C.

    Establish regular multi-stakeholder meetings to ensure all groups receive the same information simultaneously

    D.

    Assign dedicated communication coordinators to each major stakeholder group to manage their specific needs

    How to approach this question

    Look for systematic approaches that address diverse stakeholder communication needs with appropriate content, channels, timing, and feedback mechanisms.

    Full Answer

    B.Develop a detailed stakeholder communication matrix that specifies content, channels, frequency, timing, and feedback mechanisms for each group✓ Correct
    Effective communication management for complex projects requires systematic analysis of stakeholder needs and development of targeted communication approaches that address diverse requirements, preferences, and timelines.

    Common mistakes

    Students often choose centralized or uniform approaches rather than recognizing the need for stakeholder-specific communication strategies with detailed planning.
    Question 87All questionsQuestion 89

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard