For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 4Question 89
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksrisk managementcybersecurityvulnerability assessmenthybrid projects

    PMP · Question 89 · Task 3: Assess and manage risks

    During execution of a hybrid project, a new cybersecurity vulnerability is discovered that affects the project's cloud infrastructure components. Security experts indicate the vulnerability could potentially compromise data integrity and system availability if exploited. The project is 80% complete, and implementing comprehensive security updates would require 4 weeks and additional budget allocation. What should the project manager do FIRST?

    Answer options:

    A.

    Immediately implement all recommended security updates to protect against the potential vulnerability

    B.

    Continue with the current plan since the vulnerability has not been exploited and may never be targeted

    C.

    Conduct a comprehensive risk assessment to evaluate the probability, impact, and urgency of the vulnerability and develop response options

    D.

    Escalate the cybersecurity vulnerability to senior management for immediate executive decision

    How to approach this question

    Look for systematic risk assessment approaches that evaluate cybersecurity threats comprehensively and develop informed response options before making decisions.

    Full Answer

    C.Conduct a comprehensive risk assessment to evaluate the probability, impact, and urgency of the vulnerability and develop response options✓ Correct
    Effective risk management for cybersecurity threats requires comprehensive assessment of probability, impact, and urgency to develop informed response options that balance security needs with project constraints.

    Common mistakes

    Students often choose immediate action or escalation approaches rather than recognizing the need for comprehensive cybersecurity risk assessment first.
    Question 88All questionsQuestion 90

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →