Hard1 markMultiple Choice
Task 3: Assess and manage risksrisk managementcybersecurityvulnerability assessmenthybrid projects

PMP · Question 89 · Task 3: Assess and manage risks

During execution of a hybrid project, a new cybersecurity vulnerability is discovered that affects the project's cloud infrastructure components. Security experts indicate the vulnerability could potentially compromise data integrity and system availability if exploited. The project is 80% complete, and implementing comprehensive security updates would require 4 weeks and additional budget allocation. What should the project manager do FIRST?

Answer options:

A.

Immediately implement all recommended security updates to protect against the potential vulnerability

B.

Continue with the current plan since the vulnerability has not been exploited and may never be targeted

C.

Conduct a comprehensive risk assessment to evaluate the probability, impact, and urgency of the vulnerability and develop response options

D.

Escalate the cybersecurity vulnerability to senior management for immediate executive decision

How to approach this question

Look for systematic risk assessment approaches that evaluate cybersecurity threats comprehensively and develop informed response options before making decisions.

Full Answer

C.Conduct a comprehensive risk assessment to evaluate the probability, impact, and urgency of the vulnerability and develop response options✓ Correct
C
Effective risk management for cybersecurity threats requires comprehensive assessment of probability, impact, and urgency to develop informed response options that balance security needs with project constraints.

Common mistakes

Students often choose immediate action or escalation approaches rather than recognizing the need for comprehensive cybersecurity risk assessment first.