Hard1 markMultiple Choice
PMP · Question 22 · Task 8: Plan and manage scope
During sprint planning, the product owner presents new high-priority user stories that were not in the original product backlog. The development team expresses concern that adding these stories will impact their ability to complete previously committed work. What should the project manager do FIRST?
During sprint planning, the product owner presents new high-priority user stories that were not in the original product backlog. The development team expresses concern that adding these stories will impact their ability to complete previously committed work. What should the project manager do FIRST?
Answer options:
A.
Add the new stories to the sprint since they are high priority from the product owner
B.
Reject the new stories since they weren't in the original sprint plan
C.
Facilitate a discussion about capacity, priorities, and trade-offs to determine the best approach
D.
Ask the team to work overtime to accommodate both the original and new work
How to approach this question
Look for collaborative approaches that balance business needs with team capacity and sustainable practices.
Full Answer
C.Facilitate a discussion about capacity, priorities, and trade-offs to determine the best approach✓ Correct
C
Effective scope management in agile requires facilitating discussions about capacity, priorities, and trade-offs rather than simply accepting or rejecting changes.
Common mistakes
Automatically accepting high-priority requests without considering capacity, or rigidly rejecting changes without exploring options.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert