Hard1 markMultiple Choice
Task 12: Manage project artifactsartifact managementversion controlinformation managementcentralized repository

PMP · Question 26 · Task 12: Manage project artifacts

A project manager discovers that project artifacts are stored in multiple locations with different version control systems, and team members are sometimes working with outdated information. This has led to rework and confusion. What should the project manager do FIRST?

Answer options:

A.

Establish a centralized repository with clear version control and access procedures

B.

Send an email to all team members about the importance of using current versions

C.

Assign a team member to manually check that everyone has current versions

D.

Schedule weekly meetings to review which artifacts have been updated

How to approach this question

Look for systematic solutions that address the root cause of artifact management problems rather than treating symptoms.

Full Answer

A.Establish a centralized repository with clear version control and access procedures✓ Correct
A
Effective artifact management requires centralized storage with proper version control and access procedures to ensure all team members work with current information.

Common mistakes

Focusing on communication solutions rather than systemic fixes, or creating manual processes instead of systematic solutions.