Hard1 markMultiple Choice
PMP · Question 52 · Task 3: Assess and manage risks
During iteration planning, the team identifies a new technical risk: the third-party payment processing API may not handle the expected transaction volume during peak periods. This could impact the upcoming release. What should the project manager do FIRST?
During iteration planning, the team identifies a new technical risk: the third-party payment processing API may not handle the expected transaction volume during peak periods. This could impact the upcoming release. What should the project manager do FIRST?
Answer options:
A.
Add the risk to the risk register and schedule detailed analysis for the next iteration
B.
Remove the payment processing feature from the current iteration to avoid the risk
C.
Conduct a spike to test the API's capacity limits and identify potential solutions
D.
Escalate the risk to the product owner for a scope decision
How to approach this question
Look for approaches that provide quick technical risk assessment and solution exploration, especially in agile contexts where rapid feedback is valuable.
Full Answer
C.Conduct a spike to test the API's capacity limits and identify potential solutions✓ Correct
In agile environments, conducting spikes to quickly assess technical risks through testing and explore solutions provides the rapid feedback needed for informed decision-making.
Common mistakes
Delaying technical risk assessment, making premature scope decisions, or escalating without sufficient technical information gathering.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert