    PracticePMI PMP®PMI PMP Practice Exam 6Question 58
    Hard1 markMultiple Choice
    Task 9: Integrate project planning activitiesproject integrationdependency analysisresource conflictsbusiness value

    PMP · Question 58 · Task 9: Integrate project planning activities

    A project manager is integrating plans from multiple workstreams for a large digital transformation. During integration, they discover resource conflicts between workstreams, timeline gaps that could delay value delivery, and dependencies that weren't previously identified. What should the project manager do FIRST?

    Answer options:

    A.

    Conduct a comprehensive analysis of the conflicts, gaps, and dependencies to understand their impact on business value delivery

    B.

    Prioritize the workstream with the highest business value and adjust others accordingly

    C.

    Request additional resources to resolve all identified conflicts and gaps

    D.

    Escalate the integration issues to the transformation steering committee

    How to approach this question

    Look for systematic analysis approaches that understand the full scope of integration issues before jumping to solutions or escalation.

    Full Answer

    A.Conduct a comprehensive analysis of the conflicts, gaps, and dependencies to understand their impact on business value delivery✓ Correct
    Effective project integration requires systematic analysis of all conflicts, gaps, and dependencies to understand their collective impact on business value delivery before developing appropriate solutions.

    Common mistakes

    Jumping to solutions without proper analysis, making unilateral prioritization decisions, or escalating without providing comprehensive analysis and options.
    Question 57All questionsQuestion 59

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard