PMP · Question 58 · Task 9: Integrate project planning activities
A project manager is integrating plans from multiple workstreams for a large digital transformation. During integration, they discover resource conflicts between workstreams, timeline gaps that could delay value delivery, and dependencies that weren't previously identified. What should the project manager do FIRST?
A project manager is integrating plans from multiple workstreams for a large digital transformation. During integration, they discover resource conflicts between workstreams, timeline gaps that could delay value delivery, and dependencies that weren't previously identified. What should the project manager do FIRST?
Answer options:
Conduct a comprehensive analysis of the conflicts, gaps, and dependencies to understand their impact on business value delivery
Prioritize the workstream with the highest business value and adjust others accordingly
Request additional resources to resolve all identified conflicts and gaps
Escalate the integration issues to the transformation steering committee
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
Expert