PMP · Question 90 · Task 6: Plan and manage schedule
A project manager is developing a schedule for a complex integration project. The critical path includes: Requirements Analysis (4 days), System Design (10 days), Development (15 days), Integration Testing (8 days), and User Acceptance Testing (5 days). If Integration Testing can begin 3 days before Development is complete (fast-tracking), what is the new critical path duration?
Answer options:
42 days
40 days
39 days
37 days