Hard1 markMultiple Choice
PMP · Question 90 · Task 6: Plan and manage schedule
A project manager is developing a schedule for a complex integration project. The critical path includes: Requirements Analysis (4 days), System Design (10 days), Development (15 days), Integration Testing (8 days), and User Acceptance Testing (5 days). If Integration Testing can begin 3 days before Development is complete (fast-tracking), what is the new critical path duration?
A project manager is developing a schedule for a complex integration project. The critical path includes: Requirements Analysis (4 days), System Design (10 days), Development (15 days), Integration Testing (8 days), and User Acceptance Testing (5 days). If Integration Testing can begin 3 days before Development is complete (fast-tracking), what is the new critical path duration?
Answer options:
A.
42 days
B.
40 days
C.
39 days
D.
37 days
How to approach this question
Calculate the overlap carefully: Integration Testing starts 3 days before Development ends, creating a 3-day overlap that reduces total duration.
Full Answer
C.39 days✓ Correct
C
With fast-tracking, Integration Testing starts 3 days before Development completes, creating overlap. Total duration = 4 + 10 + (15 + 8 - 3) + 5 = 39 days, saving 3 days from the original 42-day duration.
Common mistakes
Not accounting for the overlap correctly, adding the overlap instead of subtracting it, or miscalculating the parallel work duration.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert