Hard1 markMultiple Choice
Task 6: Plan and manage scheduleschedule managementfast-trackingcritical pathactivity overlap

PMP · Question 90 · Task 6: Plan and manage schedule

A project manager is developing a schedule for a complex integration project. The critical path includes: Requirements Analysis (4 days), System Design (10 days), Development (15 days), Integration Testing (8 days), and User Acceptance Testing (5 days). If Integration Testing can begin 3 days before Development is complete (fast-tracking), what is the new critical path duration?

Answer options:

A.

42 days

B.

40 days

C.

39 days

D.

37 days

How to approach this question

Calculate the overlap carefully: Integration Testing starts 3 days before Development ends, creating a 3-day overlap that reduces total duration.

Full Answer

C.39 days✓ Correct
C
With fast-tracking, Integration Testing starts 3 days before Development completes, creating overlap. Total duration = 4 + 10 + (15 + 8 - 3) + 5 = 39 days, saving 3 days from the original 42-day duration.

Common mistakes

Not accounting for the overlap correctly, adding the overlap instead of subtracting it, or miscalculating the parallel work duration.