PMP · Question 98 · Task 14: Establish project governance structure
A project manager is establishing governance for a complex international project involving multiple vendors across different countries, regulatory compliance in five jurisdictions, and integration with existing enterprise systems. The organization has standard governance structures, but this project has unique international complexity, regulatory, and integration risk factors. What should the project manager do FIRST?
A project manager is establishing governance for a complex international project involving multiple vendors across different countries, regulatory compliance in five jurisdictions, and integration with existing enterprise systems. The organization has standard governance structures, but this project has unique international complexity, regulatory, and integration risk factors. What should the project manager do FIRST?
Answer options:
Implement the organization's standard governance structure without modifications to maintain consistency
Assess organizational governance and adapt it to address the project's specific international, regulatory, and integration complexity requirements
Create entirely new governance structures designed specifically for complex international projects
Delegate governance establishment to the lead international vendor since they have multi-country experience