Easy1 markMultiple Choice
PMP · Question 112 · Task 8: Plan and manage scope
A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is delivering value. The PM uses 'User Stories'. What is the format?
A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is delivering value. The PM uses 'User Stories'. What is the format?
Answer options:
A.
The system shall...
B.
As a <role>, I want <feature>, so that <benefit>.
C.
Feature: <name>.
D.
Task: <description>.
How to approach this question
Role + Goal + Benefit.
Full Answer
B.As a <role>, I want <feature>, so that <benefit>.✓ Correct
B
Task 8 (Scope). User stories focus on the user and the value (benefit), not just the function.
Common mistakes
Forgetting the 'So that' (Benefit) clause.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert