Easy1 markMultiple Choice

PMP · Question 112 · Task 8: Plan and manage scope

A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is delivering value. The PM uses 'User Stories'. What is the format?

Answer options:

A.

The system shall...

B.

As a <role>, I want <feature>, so that <benefit>.

C.

Feature: <name>.

D.

Task: <description>.

How to approach this question

Role + Goal + Benefit.

Full Answer

B.As a <role>, I want <feature>, so that <benefit>.✓ Correct
B
Task 8 (Scope). User stories focus on the user and the value (benefit), not just the function.

Common mistakes

Forgetting the 'So that' (Benefit) clause.