PMP · Question 34 · Task 12: Manage project artifacts
A project manager is using a burnup chart to track progress. The 'Total Scope' line has recently jumped up significantly, while the 'Completed Work' line is rising steadily. What does this indicate?
Answer options:
The team's velocity has increased.
New requirements have been added to the project (Scope Creep or Change).
The project is ahead of schedule.
The team is finding fewer defects.
114 questions · hints · full answers · grading