PMP · Question 35 · Task 1: Plan and manage project compliance
A project manager is leading a project with a fixed budget. A key stakeholder demands a change that is critical for compliance but will cause a budget overrun. What should the project manager do?
Answer options:
Reject the change due to the fixed budget.
Implement the change and hope to save money elsewhere.
Analyze the impact and submit a change request to the governance board requesting additional funds or scope reduction elsewhere.