Hard1 markMultiple Choice

PMP · Question 36 · Task 14: Establish project governance structure

A project manager is taking over an existing project. They want to understand who has the authority to approve changes and what the escalation limits are. Which document should they review?

Answer options:

A.

Stakeholder Register

B.

Project Management Plan (specifically the Governance/Change Management Plan)

C.

Project Charter

D.

RACI Matrix

How to approach this question

Authority/Rules = Governance.

Full Answer

B.Project Management Plan (specifically the Governance/Change Management Plan)✓ Correct
B
Task 14 (Establish project governance structure). Governance defines the framework for decision making.

Common mistakes

Confusing RACI (Task level) with Governance (Project level).

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam