    PracticePMI PMP®PMI PMP Practice ExamQuestion 37
    Hard1 markMultiple Choice
    Task 14: Promote team performance through EIPeopleFacilitationRetrospective

    PMP · Question 37 · Task 14: Promote team performance through EI

    A project manager is facilitating a retrospective. The team is quiet and reluctant to share negative feedback. The PM suggests playing a game where team members write anonymous notes about what went well and what didn't. Which technique is the PM using?

    Answer options:

    A.

    Root Cause Analysis

    B.

    Nominal Group Technique

    C.

    Facilitation / Emotional Intelligence to build safety

    D.

    Delphi Technique

    How to approach this question

    Identify the skill. The PM is reading the room (EI) and using a tool to help (Facilitation).

    Full Answer

    C.Facilitation / Emotional Intelligence to build safety✓ Correct
    C
    Task 14 (EI) and Task 2 (Lead). The PM adapts their style to the team's needs. Anonymous input is a standard facilitation tactic for low-safety environments.

    Common mistakes

    Focusing on the specific name of the game rather than the intent/skill.
    Question 36All questionsQuestion 38

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →