    PracticePMI PMP®PMI PMP Practice ExamQuestion 44
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentCompliance

    PMP · Question 44 · Task 1: Plan and manage project compliance

    A project manager is planning a project that involves sensitive personal data. The PM identifies a risk of data leakage. Which action represents 'Privacy by Design'?

    Answer options:

    A.

    Planning to audit the system after it is built.

    B.

    Incorporating data encryption and access controls into the architectural requirements from the very beginning.

    C.

    Buying insurance against data breaches.

    D.

    Training the team on data privacy laws.

    How to approach this question

    Compliance (Task 1). 'By Design' means it's in the blueprints, not added on later.

    Full Answer

    B.Incorporating data encryption and access controls into the architectural requirements from the very beginning.✓ Correct
    Task 1 (Compliance). Privacy by Design is a modern standard (GDPR etc.). It requires compliance to be a functional requirement, not an afterthought.

    Common mistakes

    Thinking training or insurance covers 'Design'.
    Question 43All questionsQuestion 45

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →