PMP · Question 70 · Task 5: Plan and manage budget and resources
A project manager is reviewing the project resource plan. They notice that a critical expert is over-allocated (booked 150%) in the next month. What technique should the PM use to resolve this?
Answer options:
Resource Smoothing
Resource Leveling
Crashing
Fast Tracking