For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 70
    Medium1 markMultiple Choice
    Task 5: Plan and manage budget and resourcesProcessResourcesSchedule

    PMP · Question 70 · Task 5: Plan and manage budget and resources

    A project manager is reviewing the project resource plan. They notice that a critical expert is over-allocated (booked 150%) in the next month. What technique should the PM use to resolve this?

    Answer options:

    A.

    Resource Smoothing

    B.

    Resource Leveling

    C.

    Crashing

    D.

    Fast Tracking

    How to approach this question

    Over-allocation -> Leveling.

    Full Answer

    B.Resource Leveling✓ Correct
    B
    Task 5 (Resources). Resource Leveling is the technique to resolve over-allocation constraints, usually by delaying tasks.

    Common mistakes

    Confusing Smoothing (optimizing within time limits) with Leveling (resolving constraints, potentially changing time).
    Question 69All questionsQuestion 71

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →