A project manager is leading a project to build a new data center. The project is 50% complete. A new technology is released that would make the data center 20% more efficient but would require a significant redesign. What should the PM do?
A project manager is leading a project to build a new data center. The project is 50% complete. A new technology is released that would make the data center 20% more efficient but would require a significant redesign. What should the PM do?
Answer options:
A.
Ignore the new technology to stay on schedule.
B.
Implement the new technology immediately.
C.
Analyze the cost-benefit of the change (Redesign cost vs Efficiency gain) and present a business case to the Change Control Board.
D.
Ask the team to vote.
How to approach this question
Opportunity -> Business Case -> Decision.
Full Answer
C.Analyze the cost-benefit of the change (Redesign cost vs Efficiency gain) and present a business case to the Change Control Board.✓ Correct
C
Task 1 (Value) and Task 10 (Changes). Opportunities are positive risks. The PM must evaluate if the opportunity adds enough value to justify the change cost.
Common mistakes
Ignoring innovation (A) or chasing it blindly (B).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert