PMP · Question 76 · Task 7: Address and remove impediments
A project manager is leading a team that is constantly interrupted by operational requests from other departments. The team's velocity is suffering. What should the PM do?
A project manager is leading a team that is constantly interrupted by operational requests from other departments. The team's velocity is suffering. What should the PM do?
Answer options:
A.
Tell the team to work harder.
B.
Act as a shield for the team, intercepting requests and negotiating their priority or deferring them.
C.
Allow the interruptions as they are important to the company.
D.
Move the team to a secret location.
How to approach this question
Servant Leader = Shield.
Full Answer
B.Act as a shield for the team, intercepting requests and negotiating their priority or deferring them.✓ Correct
B
Task 7 (Impediments). Interruptions are impediments. The PM protects the team's focus.
Common mistakes
Letting the team handle the noise.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert