Medium1 markMultiple Choice

PMP · Question 76 · Task 7: Address and remove impediments

A project manager is leading a team that is constantly interrupted by operational requests from other departments. The team's velocity is suffering. What should the PM do?

Answer options:

A.

Tell the team to work harder.

B.

Act as a shield for the team, intercepting requests and negotiating their priority or deferring them.

C.

Allow the interruptions as they are important to the company.

D.

Move the team to a secret location.

How to approach this question

Servant Leader = Shield.

Full Answer

B.Act as a shield for the team, intercepting requests and negotiating their priority or deferring them.✓ Correct
B
Task 7 (Impediments). Interruptions are impediments. The PM protects the team's focus.

Common mistakes

Letting the team handle the noise.