For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 77
    Hard1 markMultiple Choice
    Task 16: Ensure knowledge transferProcessClosureLessons Learned

    PMP · Question 77 · Task 16: Ensure knowledge transfer

    A project manager is preparing the final project report. The project was a failure; it was cancelled before completion. The sponsor says, 'Just archive the files and move on. Don't waste time on a report.' What should the PM do?

    Answer options:

    A.

    Follow the sponsor's instructions.

    B.

    Write a report blaming the sponsor.

    C.

    Explain the value of documenting lessons learned from failure to prevent recurrence, and complete the report.

    D.

    File a grievance.

    How to approach this question

    Failure = Learning. Learning > Saving 2 hours.

    Full Answer

    C.Explain the value of documenting lessons learned from failure to prevent recurrence, and complete the report.✓ Correct
    Task 16 (Knowledge Transfer) and Task 17 (Closure). Lessons learned are critical assets. The PM advocates for the long-term value of the organization over the short-term desire to bury the failure.

    Common mistakes

    Thinking lessons learned are only for successful projects.
    Question 76All questionsQuestion 78

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →