Hard1 markMultiple Choice
Task 16: Ensure knowledge transferProcessClosureLessons Learned

PMP · Question 77 · Task 16: Ensure knowledge transfer

A project manager is preparing the final project report. The project was a failure; it was cancelled before completion. The sponsor says, 'Just archive the files and move on. Don't waste time on a report.' What should the PM do?

Answer options:

A.

Follow the sponsor's instructions.

B.

Write a report blaming the sponsor.

C.

Explain the value of documenting lessons learned from failure to prevent recurrence, and complete the report.

D.

File a grievance.

How to approach this question

Failure = Learning. Learning > Saving 2 hours.

Full Answer

C.Explain the value of documenting lessons learned from failure to prevent recurrence, and complete the report.✓ Correct
C
Task 16 (Knowledge Transfer) and Task 17 (Closure). Lessons learned are critical assets. The PM advocates for the long-term value of the organization over the short-term desire to bury the failure.

Common mistakes

Thinking lessons learned are only for successful projects.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam