Hard1 markMultiple Choice
PMP · Question 78 · Task 13: Determine appropriate project methodology
A project manager is leading a project to develop a new mobile app. The team is using Scrum. The Product Owner is constantly adding new stories to the current sprint. The team is frustrated. What should the PM do?
A project manager is leading a project to develop a new mobile app. The team is using Scrum. The Product Owner is constantly adding new stories to the current sprint. The team is frustrated. What should the PM do?
Answer options:
A.
Tell the team to work faster.
B.
Coach the Product Owner on the importance of the Sprint Goal and the rule that scope is fixed during the sprint.
C.
Allow the changes but extend the sprint end date.
D.
Remove the Product Owner from the team.
How to approach this question
Scrum Rules: Sprint = Protected. PO needs coaching.
Full Answer
B.Coach the Product Owner on the importance of the Sprint Goal and the rule that scope is fixed during the sprint.✓ Correct
B
Task 13 (Methodology) and Task 13 (Mentor stakeholders). The PM (Scrum Master) protects the process. Scope creep inside a sprint destroys predictability and morale.
Common mistakes
Thinking Agile means 'change anything anytime'. It means 'change at the boundaries'.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert