PMP · Question 79 · Task 2: Evaluate and deliver project benefits
A project manager is leading a project with a very tight budget. A team member suggests a creative way to automate a testing process that will save money in the long run but costs $5,000 upfront. The project does not have $5,000 in the budget. What should the PM do?
Answer options:
Reject the idea due to lack of funds.
Use the contingency reserve.
Create a business case showing the ROI (Return on Investment) and submit a change request for additional funding.
Ask the team member to pay for it.