    PracticePMI PMP®PMI PMP Practice ExamQuestion 79
    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefitsBusiness EnvironmentValueBudget

    PMP · Question 79 · Task 2: Evaluate and deliver project benefits

    A project manager is leading a project with a very tight budget. A team member suggests a creative way to automate a testing process that will save money in the long run but costs $5,000 upfront. The project does not have $5,000 in the budget. What should the PM do?

    Answer options:

    A.

    Reject the idea due to lack of funds.

    B.

    Use the contingency reserve.

    C.

    Create a business case showing the ROI (Return on Investment) and submit a change request for additional funding.

    D.

    Ask the team member to pay for it.

    How to approach this question

    Good idea + No money = Business Case.

    Full Answer

    C.Create a business case showing the ROI (Return on Investment) and submit a change request for additional funding.✓ Correct
    C
    Task 1 (Value) and Task 5 (Budget). Value delivery often requires investment. The PM facilitates the decision by providing the data (ROI).

    Common mistakes

    Rejecting improvements because 'it's not in the budget'. Budgets can change if value is proven.
    Question 78All questionsQuestion 80

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →