Medium1 markMultiple Choice

PMP · Question 80 · Task 2: Lead a team

A project manager is leading a project to build a new school. The project is on schedule. Suddenly, a massive earthquake hits the region, destroying the access roads. The project cannot continue for at least 3 months. What should the PM do FIRST?

Answer options:

A.

Update the schedule.

B.

Ensure the safety of the team.

C.

Inform the sponsor.

D.

Check the insurance policy.

How to approach this question

Disaster -> People Safety First.

Full Answer

B.Ensure the safety of the team.✓ Correct
Task 2 (Lead a team). In any emergency, the first priority is human safety.

Common mistakes

Focusing on the project artifacts (A, C, D) before the people.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam