Medium1 markMultiple Choice
PMP · Question 80 · Task 2: Lead a team
A project manager is leading a project to build a new school. The project is on schedule. Suddenly, a massive earthquake hits the region, destroying the access roads. The project cannot continue for at least 3 months. What should the PM do FIRST?
A project manager is leading a project to build a new school. The project is on schedule. Suddenly, a massive earthquake hits the region, destroying the access roads. The project cannot continue for at least 3 months. What should the PM do FIRST?
Answer options:
A.
Update the schedule.
B.
Ensure the safety of the team.
C.
Inform the sponsor.
D.
Check the insurance policy.
How to approach this question
Disaster -> People Safety First.
Full Answer
B.Ensure the safety of the team.✓ Correct
Task 2 (Lead a team). In any emergency, the first priority is human safety.
Common mistakes
Focusing on the project artifacts (A, C, D) before the people.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert