Hard1 markMultiple Choice

PMP · Question 81 · Task 1: Execute project with urgency

A project manager is leading a software project. The team is using a Kanban board. The PM notices that work items are piling up in the 'Done' column, but the customer hasn't seen them yet. What is the waste here?

Answer options:

A.

Defects

B.

Inventory (Partially Done Work / Undeployed Value).

C.

Over-processing

D.

Motion

How to approach this question

Lean Wastes. Done but not used = Inventory.

Full Answer

B.Inventory (Partially Done Work / Undeployed Value).✓ Correct
B
Task 1 (Value). Value is only delivered when the customer uses it. 'Done' on a board is not enough; it must be released.

Common mistakes

Thinking 'Done' means value is delivered.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam