PMP · Question 82 · Task 9: Collaborate with stakeholders
A project manager is leading a project to implement a new ERP system. The project affects the Finance, HR, and Sales departments. The Finance Director is the Sponsor. The HR Director is resisting the change. The Sales Director is neutral. Who is the most critical stakeholder to manage to resolve the resistance?
Answer options:
The Sales Director
The HR Director
The Finance Director (Sponsor)
The Project Team