Medium1 markMultiple Choice
Task 1: Plan and manage project complianceBusiness EnvironmentCompliance

PMP · Question 83 · Task 1: Plan and manage project compliance

A project manager is reviewing the lessons learned from a previous project. They see that the previous project failed because the team did not understand the compliance requirements. What should the PM do for the new project?

Answer options:

A.

Copy the compliance plan from the old project.

B.

Identify compliance requirements early, involve compliance experts in the planning phase, and schedule regular compliance reviews.

C.

Ignore it; this team is smarter.

D.

Assign the compliance risk to a vendor.

How to approach this question

Lesson Learned -> Action.

Full Answer

B.Identify compliance requirements early, involve compliance experts in the planning phase, and schedule regular compliance reviews.✓ Correct
B
Task 1 (Compliance) and Task 16 (Knowledge Transfer). Using lessons learned means changing your behavior to avoid past mistakes.

Common mistakes

Reading lessons learned but not acting on them.