Medium1 markMultiple Choice
PMP · Question 83 · Task 1: Plan and manage project compliance
A project manager is reviewing the lessons learned from a previous project. They see that the previous project failed because the team did not understand the compliance requirements. What should the PM do for the new project?
A project manager is reviewing the lessons learned from a previous project. They see that the previous project failed because the team did not understand the compliance requirements. What should the PM do for the new project?
Answer options:
A.
Copy the compliance plan from the old project.
B.
Identify compliance requirements early, involve compliance experts in the planning phase, and schedule regular compliance reviews.
C.
Ignore it; this team is smarter.
D.
Assign the compliance risk to a vendor.
How to approach this question
Lesson Learned -> Action.
Full Answer
B.Identify compliance requirements early, involve compliance experts in the planning phase, and schedule regular compliance reviews.✓ Correct
B
Task 1 (Compliance) and Task 16 (Knowledge Transfer). Using lessons learned means changing your behavior to avoid past mistakes.
Common mistakes
Reading lessons learned but not acting on them.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert