PMP · Question 84 · Task 14: Establish project governance structure
A project manager is leading a project to develop a new drug. The project is in Phase 2 (Clinical Trials). The results of the first trial are inconclusive. The governance board requires a 'Kill Point' review. What is the likely outcome?
Answer options:
The project will be cancelled immediately.
The project will proceed to Phase 3 automatically.
The board will review the data and decide to either: Continue, Cancel, or request Rework/Additional Trials.
The PM will be fired.