Hard1 markMultiple Choice
PMP · Question 18 · Task 5: Plan and manage budget and resources
An agile project has a fixed budget but variable scope. The sponsor wants to know how the team tracks if they are on budget. Which metric is MOST appropriate for the project manager to present?
An agile project has a fixed budget but variable scope. The sponsor wants to know how the team tracks if they are on budget. Which metric is MOST appropriate for the project manager to present?
Answer options:
A.
Schedule Performance Index (SPI)
B.
Estimate to Complete (ETC)
C.
Velocity
D.
Cost Performance Index (CPI) or Burn rate
How to approach this question
Select the metric that specifically relates money spent to value/progress.
Full Answer
D.Cost Performance Index (CPI) or Burn rate✓ Correct
D
Task 5 involves monitoring budget variations. CPI is the standard efficiency metric. Burn rate is the agile term for run rate. Both answer 'are we on budget?'.
Common mistakes
Thinking Velocity tracks budget (it tracks throughput).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert