Hard1 markMultiple Choice

PMP · Question 40 · Task 11: Plan and manage procurement

An agile project needs to outsource a specific component. The team wants to collaborate closely with the vendor, sharing risks and rewards. Which contract structure supports this?

Answer options:

A.

Standard Fixed Price

B.

Dynamic (Agile) Contract with optional scope clauses

C.

Purchase Order

D.

Cost Plus Percentage of Cost

How to approach this question

Look for the option that allows flexibility and shared goals.

Full Answer

B.Dynamic (Agile) Contract with optional scope clauses✓ Correct
B
Task 11. Agile procurement favors flexible arrangements where scope can be swapped or cancelled early (shared risk/reward).

Common mistakes

Assuming Fixed Price is safe (it's rigid).

Practice the full PMP Process Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam