Hard1 markMultiple Choice
PMP · Question 10 · Task 10: Build shared understanding
In a multi-cultural project team, a misunderstanding regarding the definition of 'Done' has led to quality issues. The team members from one region believe testing is a separate phase, while others believe it is part of development. What should the project manager do to build a shared understanding?
In a multi-cultural project team, a misunderstanding regarding the definition of 'Done' has led to quality issues. The team members from one region believe testing is a separate phase, while others believe it is part of development. What should the project manager do to build a shared understanding?
Answer options:
A.
Update the project management plan to define 'Done' and email it to the team.
B.
Assign the QA lead to define the standard and enforce it.
C.
Facilitate a workshop with the entire team to co-create a Definition of Done (DoD).
D.
Adopt the definition used by the team members with the most experience.
How to approach this question
Look for the option that involves the team in the solution (collaborative/participatory).
Full Answer
C.Facilitate a workshop with the entire team to co-create a Definition of Done (DoD).✓ Correct
C
Workshops allow for dialogue, clarification of cultural/process differences, and agreement on a single standard.
Common mistakes
Relying on documents (A) or authority (B) to solve a cultural/understanding gap.
Practice the full PMI PMP Mini Practice Exam 3
20 questions · hints · full answers · grading
More questions from this exam
Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard
Expert