    PracticePMI PMP®PMI PMP Mini Practice Exam 3Question 10
    Hard1 markMultiple Choice
    Task 10: Build shared understandingPeopleShared UnderstandingAgile

    PMP · Question 10 · Task 10: Build shared understanding

    In a multi-cultural project team, a misunderstanding regarding the definition of 'Done' has led to quality issues. The team members from one region believe testing is a separate phase, while others believe it is part of development. What should the project manager do to build a shared understanding?

    Answer options:

    A.

    Update the project management plan to define 'Done' and email it to the team.

    B.

    Assign the QA lead to define the standard and enforce it.

    C.

    Facilitate a workshop with the entire team to co-create a Definition of Done (DoD).

    D.

    Adopt the definition used by the team members with the most experience.

    How to approach this question

    Look for the option that involves the team in the solution (collaborative/participatory).

    Full Answer

    C.Facilitate a workshop with the entire team to co-create a Definition of Done (DoD).✓ Correct
    Workshops allow for dialogue, clarification of cultural/process differences, and agreement on a single standard.

    Common mistakes

    Relying on documents (A) or authority (B) to solve a cultural/understanding gap.
    Question 9All questionsQuestion 11

    Practice the full PMI PMP Mini Practice Exam 3

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard
    View all 20 questions →