Hard1 markMultiple Choice
PMP · Question 73 · Task 2: Lead a team
A project manager is leading a team that has been working remotely for eight months. While productivity remains high, team members report feeling disconnected from the project's purpose and impact. What should the project manager do to address this issue?
A project manager is leading a team that has been working remotely for eight months. While productivity remains high, team members report feeling disconnected from the project's purpose and impact. What should the project manager do to address this issue?
Answer options:
A.
Increase the frequency of team meetings to provide more connection opportunities
B.
Organize virtual team building activities to improve team cohesion
C.
Create opportunities for team members to see and understand the impact of their work on project outcomes and beneficiaries
D.
Implement individual recognition programs to increase engagement
How to approach this question
When team members feel disconnected from purpose, create opportunities for them to see and understand the impact of their work rather than just increasing social interaction.
Full Answer
C.Create opportunities for team members to see and understand the impact of their work on project outcomes and beneficiaries✓ Correct
C
Disconnection from purpose requires helping team members understand how their work contributes to meaningful outcomes and impacts beneficiaries.
Common mistakes
Focusing on social connection or general engagement rather than specifically addressing the disconnect from project purpose and impact.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert