For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 4Question 17
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksrisk managementregulatory complianceimpact assessmenthybrid projects

    PMP · Question 17 · Task 3: Assess and manage risks

    During the execution phase of a hybrid project, a new regulatory requirement is announced that could significantly impact the project's technical architecture. The requirement has a 6-month implementation deadline, but the full implications are not yet clear. The project is currently on track for delivery in 4 months. What should the project manager do FIRST?

    Answer options:

    A.

    Continue with the current plan and address the regulatory requirement in a future phase

    B.

    Immediately halt the project until the regulatory requirements are fully understood

    C.

    Conduct a rapid impact assessment to understand the scope of changes required and develop response options

    D.

    Extend the project timeline by 6 months to accommodate the new regulatory requirements

    How to approach this question

    Look for risk assessment approaches that gather information and develop options before making major project decisions.

    Full Answer

    C.Conduct a rapid impact assessment to understand the scope of changes required and develop response options✓ Correct
    C
    Effective risk management requires rapid assessment of new threats to understand their impact and develop appropriate response strategies before making project decisions.

    Common mistakes

    Students often choose immediate action approaches rather than recognizing the need to assess impact and develop options first.
    Question 16All questionsQuestion 18

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →