    PracticePMI PMP®PMI PMP Practice Exam 4Question 27
    Hard1 markMultiple Choice
    Task 13: Determine appropriate project methodology/methods and practicesmethodology selectionhybrid approachrequirements stabilityregulatory compliance

    PMP · Question 27 · Task 13: Determine appropriate project methodology/methods and practices

    A project manager is assigned to lead a new product development initiative. The product requirements are well-defined and stable, but the organization wants to incorporate user feedback throughout development and deliver value incrementally every 6 weeks. The development team has experience with both predictive and agile methodologies. Regulatory approval is required before final release. What methodology should the project manager recommend?

    Answer options:

    A.

    Pure Agile methodology to support incremental delivery and user feedback incorporation

    B.

    Predictive methodology since requirements are stable and well-defined

    C.

    Hybrid methodology combining predictive planning with iterative delivery and feedback cycles

    D.

    Iterative methodology with multiple development cycles and user reviews

    How to approach this question

    Analyze project characteristics (requirement stability, delivery preferences, regulatory needs) to select the methodology that best fits all constraints.

    Full Answer

    C.Hybrid methodology combining predictive planning with iterative delivery and feedback cycles✓ Correct
    C
    Methodology selection requires analyzing project characteristics including requirement stability, delivery preferences, team capabilities, and regulatory constraints to choose the optimal approach.

    Common mistakes

    Students often choose pure methodologies rather than recognizing when hybrid approaches better address multiple project characteristics.
    Question 26All questionsQuestion 28

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →