A project manager is preparing for a planned transition of a software development project from the development team to the operations team. The operations team has limited experience with the new technology stack and will be responsible for ongoing maintenance and support. The development team has been focused on feature delivery and has not documented many of their architectural decisions and troubleshooting procedures. What should the project manager do FIRST?

Answer options:

A.

Schedule intensive training sessions for the operations team on the new technology stack

B.

Extend the development team's involvement to provide ongoing support during the transition

C.

Conduct a knowledge transfer assessment to identify critical information gaps and develop a comprehensive transfer plan

D.

Create detailed documentation of all system components and procedures

How to approach this question

Look for systematic approaches that assess knowledge gaps and develop comprehensive transfer plans based on recipient needs.

Full Answer

C.Conduct a knowledge transfer assessment to identify critical information gaps and develop a comprehensive transfer plan✓ Correct
C
Effective knowledge transfer requires systematic assessment of existing knowledge, identification of gaps, and understanding of recipient needs to develop comprehensive transfer plans.

Common mistakes

Students often choose training or documentation approaches rather than recognizing the need to assess knowledge gaps and transfer requirements first.