PMP · Question 31 · Task 17: Plan and manage project/phase closure or transitions
A project manager is preparing for project closure of a successful digital transformation initiative. The project delivered all planned outcomes, but during execution, the team discovered several process improvements and technology optimizations that could benefit future similar projects. The organization is planning three more transformation projects in the next 18 months. What should the project manager do FIRST?
A project manager is preparing for project closure of a successful digital transformation initiative. The project delivered all planned outcomes, but during execution, the team discovered several process improvements and technology optimizations that could benefit future similar projects. The organization is planning three more transformation projects in the next 18 months. What should the project manager do FIRST?
Answer options:
Document all lessons learned and file them in the organizational knowledge repository
Organize a comprehensive lessons learned session with key stakeholders and future project teams to capture and transfer knowledge
Create templates and tools based on the process improvements for future project use
Schedule individual meetings with each future project manager to share experiences
How to approach this question
Full Answer
Common mistakes