For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 4Question 29
    Hard1 markMultiple Choice
    Task 15: Manage project issuesissue managementknowledge managementresource riskproject continuity

    PMP · Question 29 · Task 15: Manage project issues

    During project execution, a risk that was identified in the risk register has materialized into an active issue: a key technical resource has left the organization unexpectedly, and their specialized knowledge is critical for the next phase of development. The resource had been identified as a single point of failure, but knowledge transfer was planned for later in the project. What should the project manager do FIRST?

    Answer options:

    A.

    Immediately assess the scope of knowledge gap and identify the most critical information needed to continue the project

    B.

    Contact the departed resource to arrange knowledge transfer sessions

    C.

    Hire a replacement resource with similar technical expertise

    D.

    Escalate to senior management to determine how to proceed

    How to approach this question

    Look for immediate assessment approaches that understand the specific impact and prioritize critical needs for project continuity.

    Full Answer

    A.Immediately assess the scope of knowledge gap and identify the most critical information needed to continue the project✓ Correct
    A
    Effective issue management requires immediate assessment of the specific impact and prioritization of the most critical needs to maintain project momentum.

    Common mistakes

    Students often choose resource replacement or escalation approaches rather than recognizing the need to assess the specific knowledge gaps first.
    Question 28All questionsQuestion 30

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →