Task 1: Execute project with the urgency required to deliver business valueproject executionteam burnoutcapacity managementvalue delivery

PMP · Question 51 · Task 1: Execute project with the urgency required to deliver business value

A software development project is approaching a critical client deadline, but the team is showing signs of burnout from working extended hours for the past month. Quality issues are increasing, team communication is becoming strained, and two developers have requested time off. The client is applying pressure for faster delivery and has threatened to cancel the contract if the deadline is missed. What should the project manager do FIRST?

Answer options:

A.

Assess the team's current capacity and work with the client to identify the minimum viable deliverable that meets their core business needs

B.

Negotiate with the client for a timeline extension to allow the team to recover and deliver quality work

C.

Bring in additional contractors to supplement the team and maintain the delivery timeline

D.

Implement stricter quality controls and code review processes to address the increasing defects

How to approach this question

Look for approaches that balance business value delivery with team sustainability by focusing on core client needs within capacity constraints.

Full Answer

A.Assess the team's current capacity and work with the client to identify the minimum viable deliverable that meets their core business needs✓ Correct
A
Executing projects with urgency requires balancing speed with sustainability, focusing on delivering maximum business value within the team's current capacity constraints.

Common mistakes

Students often choose resource addition or timeline extension approaches rather than recognizing the need to focus on core value within capacity limits.