    Hard1 markMultiple Choice
    Task 2: Manage communicationscommunication managementstakeholder analysiscomplex projectscommunication matrix

    PMP · Question 52 · Task 2: Manage communications

    A project manager is leading a complex integration project with multiple external vendors, internal departments, and regulatory bodies. Each stakeholder group has different information needs, communication preferences, and decision-making timelines. Recent miscommunications have led to delays and rework. What should the project manager do FIRST?

    Answer options:

    A.

    Implement a centralized communication hub where all project information is stored and accessible

    B.

    Develop a comprehensive stakeholder communication matrix that defines specific content, channels, frequency, and timing for each group

    C.

    Establish regular all-stakeholder meetings to ensure everyone receives the same information simultaneously

    D.

    Assign dedicated communication liaisons to each major stakeholder group

    How to approach this question

    Look for systematic approaches that address diverse stakeholder communication needs with appropriate content, channels, and timing.

    Full Answer

    B.Develop a comprehensive stakeholder communication matrix that defines specific content, channels, frequency, and timing for each group✓ Correct
    B
    Effective communication management for complex projects requires systematic analysis of stakeholder needs and development of targeted communication approaches for different groups.

    Common mistakes

    Students often choose centralized or uniform approaches rather than recognizing the need for stakeholder-specific communication strategies.
    Question 51All questionsQuestion 53

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →