    PracticePMI PMP®PMI PMP Practice Exam 4Question 53
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksrisk managementcybersecuritythreat assessmenthybrid projects

    PMP · Question 53 · Task 3: Assess and manage risks

    During the execution of a hybrid project, a new cybersecurity threat is identified that could affect the project's cloud-based components. The threat has not yet materialized but security experts indicate it could impact data integrity and system availability. The project is 70% complete and implementing additional security measures would require 3 weeks and additional budget. What should the project manager do FIRST?

    Answer options:

    A.

    Immediately implement the additional security measures to protect against the potential threat

    B.

    Continue with the current plan since the threat has not materialized and may never occur

    C.

    Conduct a rapid risk assessment to evaluate the probability and impact of the threat and develop response options

    D.

    Escalate the security threat to senior management for immediate decision

    How to approach this question

    Look for systematic risk assessment approaches that evaluate threats and develop informed response options before making decisions.

    Full Answer

    C.Conduct a rapid risk assessment to evaluate the probability and impact of the threat and develop response options✓ Correct
    Effective risk management requires systematic assessment of identified threats to understand their probability and impact, then developing appropriate response options for informed decision-making.

    Common mistakes

    Students often choose immediate action or escalation approaches rather than recognizing the need for systematic risk assessment first.
    Question 52All questionsQuestion 54

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →