    PracticePMI PMP®PMI PMP Practice Exam 4Question 81
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersstakeholder collaborationdigital transformationshared visioncross-functional alignment

    PMP · Question 81 · Task 9: Collaborate with stakeholders

    A project manager is working on a digital transformation initiative involving five business units with different strategic priorities and success metrics. The marketing unit wants customer analytics capabilities, the sales unit prioritizes mobile CRM access, the finance unit focuses on automated reporting, the operations unit emphasizes process optimization, and the IT unit stresses security and system integration. What should the project manager do FIRST?

    Answer options:

    A.

    Facilitate cross-functional workshops to identify shared business objectives and create an integrated transformation vision

    B.

    Prioritize requirements based on organizational strategic importance and resource availability

    C.

    Create separate transformation tracks for each business unit to address their specific priorities

    D.

    Escalate to executive leadership to define unified transformation priorities and success metrics

    How to approach this question

    Look for collaborative approaches that build shared understanding and integrated vision among diverse business units before making transformation decisions.

    Full Answer

    A.Facilitate cross-functional workshops to identify shared business objectives and create an integrated transformation vision✓ Correct
    Effective stakeholder collaboration for digital transformation requires building shared understanding and integrated vision among diverse business units with different priorities before making decisions about transformation direction.

    Common mistakes

    Students often choose prioritization or separation approaches rather than recognizing the need to build stakeholder alignment and shared vision first.
    Question 80All questionsQuestion 82

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard