A key stakeholder who was initially supportive of the project has become increasingly critical and is questioning project decisions in public forums. This is affecting team morale and other stakeholder confidence. What should the project manager do FIRST?
A key stakeholder who was initially supportive of the project has become increasingly critical and is questioning project decisions in public forums. This is affecting team morale and other stakeholder confidence. What should the project manager do FIRST?
Answer options:
A.
Address the stakeholder's concerns publicly to demonstrate transparency
B.
Document the stakeholder's behavior and escalate to the sponsor
C.
Schedule a private meeting with the stakeholder to understand their concerns and rebuild trust
D.
Limit the stakeholder's access to project information to prevent further criticism
How to approach this question
Look for collaborative approaches that seek to understand stakeholder concerns and rebuild relationships rather than confrontational or avoidance strategies.
Full Answer
C.Schedule a private meeting with the stakeholder to understand their concerns and rebuild trust✓ Correct
C
Effective stakeholder collaboration requires understanding changing stakeholder positions and working to rebuild trust and alignment when relationships deteriorate.
Common mistakes
Choosing confrontational approaches, premature escalation, or avoidance strategies that don't address the root relationship issues.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert