    PracticePMI PMP®PMI PMP Practice Exam 6Question 13
    Hard1 markMultiple Choice
    Task 13: Mentor relevant stakeholdersmentoringcoachingskill developmentjunior project managers

    PMP · Question 13 · Task 13: Mentor relevant stakeholders

    A junior project manager on the team approaches the senior project manager asking for guidance on handling a difficult stakeholder situation. The junior PM seems overwhelmed and unsure how to proceed. What should the senior project manager do FIRST as a mentor?

    Answer options:

    A.

    Listen to understand the situation fully and ask questions to help the junior PM think through potential approaches

    B.

    Provide specific step-by-step instructions on how to handle the stakeholder situation

    C.

    Take over the stakeholder situation to ensure it's handled properly

    D.

    Refer the junior PM to training resources on stakeholder management

    How to approach this question

    Look for mentoring approaches that develop the mentee's thinking and problem-solving skills rather than providing immediate solutions.

    Full Answer

    A.Listen to understand the situation fully and ask questions to help the junior PM think through potential approaches✓ Correct
    A
    Effective mentoring uses coaching techniques to develop the mentee's thinking and problem-solving capabilities rather than simply providing solutions.

    Common mistakes

    Providing immediate solutions instead of developing thinking skills, or taking over the situation rather than using it as a learning opportunity.
    Question 12All questionsQuestion 14

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →