PMP · Question 33 · Task 2: Evaluate and deliver project benefits and value
A project manager is leading a digital transformation initiative that is expected to generate significant cost savings and efficiency improvements. However, six months into the project, stakeholders are questioning whether the promised benefits are being realized. What should the project manager do FIRST?
Answer options:
Reassure stakeholders that benefits will be realized once the project is complete
Accelerate project delivery to start realizing benefits sooner
Review the benefits measurement system and provide stakeholders with current progress data
Schedule a workshop to redefine the expected benefits with stakeholders