Hard1 markMultiple Choice
Task 1: Plan and manage project complianceregulatory complianceFDA regulationscompliance violationsrisk containment
PMP · Question 32 · Task 1: Plan and manage project compliance
A pharmaceutical company project must comply with FDA regulations throughout development. The project manager discovers that a team member unknowingly used a non-compliant data storage method for clinical trial information. What should the project manager do FIRST?
A pharmaceutical company project must comply with FDA regulations throughout development. The project manager discovers that a team member unknowingly used a non-compliant data storage method for clinical trial information. What should the project manager do FIRST?
Answer options:
A.
Document the compliance violation in the risk register for future reference
B.
Immediately halt the affected work and assess the compliance impact with regulatory experts
C.
Report the team member to HR for not following established procedures
D.
Update the project management plan to include additional compliance training
How to approach this question
In regulated industries, compliance violations require immediate containment and expert assessment before any other actions.
Full Answer
B.Immediately halt the affected work and assess the compliance impact with regulatory experts✓ Correct
B
Compliance violations in regulated industries like pharmaceuticals require immediate containment to prevent further violations and expert assessment to determine the full impact and required remediation.
Common mistakes
Focusing on documentation or training before addressing the immediate compliance risk, or treating this as a personnel issue rather than a compliance issue.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert