A pharmaceutical company project must comply with FDA regulations throughout development. The project manager discovers that a team member unknowingly used a non-compliant data storage method for clinical trial information. What should the project manager do FIRST?
Answer options:
Document the compliance violation in the risk register for future reference
Immediately halt the affected work and assess the compliance impact with regulatory experts
Report the team member to HR for not following established procedures
Update the project management plan to include additional compliance training