PMP · Question 31 · Task 17: Plan and manage project/phase closure or transitions
A project is approaching completion, and the project manager needs to transition the deliverables to the operations team. The operations team has expressed concerns about their readiness to support the new system, and some final testing is still in progress. What should the project manager do FIRST?
Answer options:
Complete all testing before beginning any transition activities
Assess the operations team's readiness and develop a transition plan that addresses their concerns
Schedule the transition for after all project activities are complete
Provide the operations team with all project documentation for their review
100 questions · hints · full answers · grading