Hard1 markMultiple Choice
Task 17: Plan and manage project/phase closure or transitionsproject closuretransition planningoperations readinessdeliverable handover
PMP · Question 31 · Task 17: Plan and manage project/phase closure or transitions
A project is approaching completion, and the project manager needs to transition the deliverables to the operations team. The operations team has expressed concerns about their readiness to support the new system, and some final testing is still in progress. What should the project manager do FIRST?
A project is approaching completion, and the project manager needs to transition the deliverables to the operations team. The operations team has expressed concerns about their readiness to support the new system, and some final testing is still in progress. What should the project manager do FIRST?
Answer options:
A.
Complete all testing before beginning any transition activities
B.
Assess the operations team's readiness and develop a transition plan that addresses their concerns
C.
Schedule the transition for after all project activities are complete
D.
Provide the operations team with all project documentation for their review
How to approach this question
Look for approaches that assess the receiving team's readiness and address their specific concerns about the transition.
Full Answer
B.Assess the operations team's readiness and develop a transition plan that addresses their concerns✓ Correct
B
Successful project transitions require assessing the receiving team's readiness and addressing their specific concerns to ensure they can effectively support the deliverables.
Common mistakes
Focusing only on project completion without considering receiving team readiness, or assuming documentation is sufficient for transition support.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert