Hard1 markMultiple Choice
Task 17: Plan and manage project/phase closure or transitionsproject closuretransition planningoperations readinessdeliverable handover

PMP · Question 31 · Task 17: Plan and manage project/phase closure or transitions

A project is approaching completion, and the project manager needs to transition the deliverables to the operations team. The operations team has expressed concerns about their readiness to support the new system, and some final testing is still in progress. What should the project manager do FIRST?

Answer options:

A.

Complete all testing before beginning any transition activities

B.

Assess the operations team's readiness and develop a transition plan that addresses their concerns

C.

Schedule the transition for after all project activities are complete

D.

Provide the operations team with all project documentation for their review

How to approach this question

Look for approaches that assess the receiving team's readiness and address their specific concerns about the transition.

Full Answer

B.Assess the operations team's readiness and develop a transition plan that addresses their concerns✓ Correct
B
Successful project transitions require assessing the receiving team's readiness and addressing their specific concerns to ensure they can effectively support the deliverables.

Common mistakes

Focusing only on project completion without considering receiving team readiness, or assuming documentation is sufficient for transition support.

Practice the full PMI PMP Practice Exam 6

100 questions · hints · full answers · grading

More questions from this exam