For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 6Question 30
    Hard1 markMultiple Choice
    Task 16: Ensure knowledge transfer for project continuityknowledge transferteam transitionsknowledge managementproject continuity

    PMP · Question 30 · Task 16: Ensure knowledge transfer for project continuity

    A project manager is preparing for a planned team member transition where a senior developer will be leaving the project in two weeks. The developer has been working on critical system components and has significant project knowledge. What should the project manager do FIRST to ensure knowledge transfer?

    Answer options:

    A.

    Work with the departing developer to identify critical knowledge areas and create a structured transfer plan

    B.

    Ask the developer to document all their work before leaving

    C.

    Schedule meetings between the departing developer and their replacement

    D.

    Have the developer train the entire team on their work areas

    How to approach this question

    Look for systematic approaches that identify what knowledge needs to be transferred and create structured plans for effective transfer.

    Full Answer

    A.Work with the departing developer to identify critical knowledge areas and create a structured transfer plan✓ Correct
    Effective knowledge transfer requires systematic identification of critical knowledge areas and structured planning to ensure comprehensive and effective transfer.

    Common mistakes

    Relying on general documentation, assuming knowledge transfer will happen naturally, or not focusing on the most critical knowledge areas.
    Question 29All questionsQuestion 31

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →