PMP · Question 29 · Task 15: Manage project issues
A project manager identifies that a previously identified risk has materialized: a key team member has left the company unexpectedly, and their departure is causing delays in critical path activities. What should the project manager do FIRST?
Answer options:
Update the risk register to show the risk has become an issue
Begin recruiting a replacement for the departed team member
Assess the immediate impact and collaborate with stakeholders to determine the optimal response
Implement the pre-planned risk response that was developed for this scenario
100 questions · hints · full answers · grading