PMP · Question 41 · Task 6: Build a team
A project manager is forming a team for a complex integration project that requires expertise in legacy systems, cloud technologies, data analytics, and user experience design. The organization has limited resources with these specific skills. What should the project manager do FIRST?
A project manager is forming a team for a complex integration project that requires expertise in legacy systems, cloud technologies, data analytics, and user experience design. The organization has limited resources with these specific skills. What should the project manager do FIRST?
Answer options:
A.
Request additional budget to hire external consultants for all required skills
B.
Form the team with available resources and plan to train them in missing skills
C.
Map required skills to available internal resources and identify specific gaps that need to be filled
D.
Reduce project scope to match available internal capabilities
How to approach this question
Look for systematic approaches that optimize use of available resources while identifying specific gaps that need to be addressed.
Full Answer
C.Map required skills to available internal resources and identify specific gaps that need to be filled✓ Correct
C
Effective team building requires systematic analysis of required skills versus available resources to optimize internal capabilities and identify specific external needs.
Common mistakes
Immediately seeking external resources without assessing internal capabilities, or compromising project objectives without exploring resource options.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert