A project team is transitioning from waterfall to agile methodology for a new project. Team members have varying levels of agile experience, and some express anxiety about the change. What should the project manager do FIRST to ensure adequate training?

Answer options:

A.

Conduct a skills assessment to identify specific agile competency gaps across the team

B.

Provide comprehensive agile training to all team members regardless of experience

C.

Pair experienced agile practitioners with those new to agile methodology

D.

Start with basic agile concepts and gradually introduce more advanced practices

How to approach this question

Look for systematic approaches that assess current state before determining training solutions.

Full Answer

A.Conduct a skills assessment to identify specific agile competency gaps across the team✓ Correct
A
Effective training programs start with assessing current competencies to identify specific gaps, ensuring training resources are used efficiently and address actual needs.

Common mistakes

Assuming what training is needed without assessment, or providing generic training that doesn't address specific team needs.