    PracticePMI PMP®PMI PMP Practice Exam 6Question 39
    Hard1 markMultiple Choice
    Task 4: Empower team members and stakeholdersempowermentdecision-making authorityarchitectural decisionsbounded autonomy

    PMP · Question 39 · Task 4: Empower team members and stakeholders

    A senior team member with deep technical expertise asks for authority to make architectural decisions for their component without requiring approval for each decision. They have consistently delivered high-quality work and other team members trust their judgment. What should the project manager do to empower this team member appropriately?

    Answer options:

    A.

    Grant full architectural decision-making authority with no oversight

    B.

    Define clear boundaries for architectural decisions and establish regular check-in points for alignment

    C.

    Maintain current approval processes to ensure consistency across all components

    D.

    Require the team member to document all decisions for review after implementation

    How to approach this question

    Look for balanced approaches that provide autonomy appropriate to competence while maintaining necessary alignment and oversight.

    Full Answer

    B.Define clear boundaries for architectural decisions and establish regular check-in points for alignment✓ Correct
    Effective empowerment provides decision-making authority appropriate to the person's competence and the impact of their decisions, with clear boundaries and alignment mechanisms.

    Common mistakes

    Granting complete autonomy without boundaries, or maintaining excessive control that doesn't recognize competence and expertise.
    Question 38All questionsQuestion 40

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →