For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 6Question 62
    Hard1 markMultiple Choice
    Task 13: Determine appropriate project methodology/methods and practicesmethodology selectionhybrid approachUI/UX developmentstable requirements

    PMP · Question 62 · Task 13: Determine appropriate project methodology/methods and practices

    A project manager is assigned to lead a new mobile application development project. The client has well-defined functional requirements that are unlikely to change, but wants to see working prototypes every three weeks to provide feedback on user interface and user experience design. Which development approach is MOST appropriate?

    Answer options:

    A.

    Pure Waterfall - Requirements are stable and well-defined

    B.

    Pure Agile - Client wants regular feedback and iterative delivery

    C.

    Hybrid - Stable functional requirements with iterative UI/UX development and feedback

    D.

    Iterative - Multiple cycles allow for continuous UI/UX refinement

    How to approach this question

    Match methodology characteristics to project needs: stable functional requirements suggest predictive elements, while UI/UX feedback needs suggest iterative elements.

    Full Answer

    C.Hybrid - Stable functional requirements with iterative UI/UX development and feedback✓ Correct
    Hybrid methodologies are ideal when different aspects of a project have different characteristics - stable functional requirements can be planned predictively while UI/UX elements benefit from iterative development and feedback.

    Common mistakes

    Choosing pure methodologies without considering all project characteristics, or not recognizing when different project aspects need different approaches.
    Question 61All questionsQuestion 63

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →